Tower Crane Installation Process: Erecting the Tower and Extending the Boom Arm

Jac 4.5Tons Articulated Bucket Lift Truck

Tower cranes with telescopic tower structures and horizontal jib configurations, such as the QT16-type quick-assembly lower slewing tower crane, often follow a sequential procedure for installation. Below is a detailed step-by-step guide:

Fotos 4.5 Tons Side Lifter Crane

1. Stabilizing the Base Frame

  • Extend all four support legs and lower the support jacks to lift the tires off the ground.
  • Adjust the main beams of the base frame to ensure they are level.
  • Secure sturdy pads beneath the support legs for stability.

2. Preparing the Boom

  • Straighten the jib by disconnecting the linkage pin from the boom head. This action detaches the linkage from the boom head.
  • Rotate the boom head to align it with the boom tail, forming a straight line.
  • Fasten the lower chords of the boom head and boom tail tightly using bolts.
  • Remove the linkage from the boom tail.

3. Aligning Tower Top Braces

  • Pull the top support rods of the tower downward until the lower support rods align in a straight line.
  • Secure the alignment with pins.

4. Inspecting the Support Cables

  • Ensure that the brace cables are positioned correctly on the upper chord at the rear of the jib.

Jac 4.5Tons Articulated Bucket Lift Truck

5. Adjusting the Hoisting Trolley

  • Remove the locking pin securing the hoisting trolley to the jib structure.
  • Tighten the front and rear adjustment bolts on the trolley, ensuring the pulling ropes are tensioned.

6. Deploying the Steel Wire Rope

  • Extend approximately 20 meters of hoisting steel wire rope.

7. Preparing the Ground for Tower and Boom Movement

  • Place a steel plate approximately 500 mm wide diagonally on the towing beam of the front axle.
  • Lay a steel plate (400 mm × 6000 mm) along the crane’s longitudinal axis in front of the boom to serve as a sliding path for the boom head during tower erection.

8. Erecting the Tower and Extending the Boom

  • Operate the dual-drum hoist from the lower control panel to begin the erection process.
  • Anfänglich, lift the tower body slightly using the hoist to detach the transport linkage securing the upper tower section to the slewing platform.
  • Continue operating the hoist to fully erect the tower. As the tower body rises, the boom head descends, sliding outward along the steel plate track.
  • Align the tower base with the corresponding holes on the slewing platform and secure them with connecting pins and fixed shaft plates.

Fotos 4.5 Tonnen artikulierter Eimer Lift -LKW

9. Setting Up Structural Cables

  • Install the boom pull ropes, tower top brace cables, telescopic adjustment ropes, and luffing ropes.
  • Verify the upper end of the outer tower body has no tightened spiral jacks.

10. Adjusting the Inner Tower Section

  • Lift the inner tower section 20–25 mm using the hoist.
  • Remove the fixing plates on the connecting pins of the inner and outer tower bodies.
  • Slightly withdraw the connecting pins to disengage them from the inner tower structure. Secure the pins with screws to prevent unintended re-engagement.

11. Extending the Inner Tower Section

  • Operate the hoist to raise the inner tower section.
  • During this process, the boom head slides inward along the inclined steel plate track, moving up and aligning closer to the tower body.
  • Ensure the boom head is guided carefully using cables to prevent the hoisting trolley from colliding with the tower structure.
  • Once the inner tower section fully extends to its limit, the boom head will automatically unfold.
  • Remove the guiding cables and continue extending the inner tower until the limit switch activates, cutting off the power.
  • Throughout this operation, ensure no cables are damaged or torn.

Sanhuan Shitong 12 Tonnen-Rollback-Carrier

12. Securing the Inner and Outer Tower Sections

  • Loosen the positioning screws of the connecting pins between the inner and outer tower bodies.
  • Push the connecting pins inward to lock the sections together.
  • Lower the inner tower using the hoist and secure the pins with axle-end plates.

13. Adjusting the Spiral Jacks

  • Tighten the four spiral jacks on the upper end of the outer tower body against the inner tower.
  • Begin with the two inner jacks before tightening the two outer ones.

14. Securing the Pulley Frame

  • Relax the installation wire rope using the hoist and dislodge the pulley frame’s axis from the outer tower body.
  • Use the same axis to connect the pulley frame with the luffing pull rope.
  • Inspect the steel wire ropes for proper alignment in their grooves.

Sanhuan Shitong 31 Tonnen-Rollback-Carrier

15. Positioning the Boom

  • Continue operating the hoist to relax the installation wire rope and raise the boom to a horizontal position.
  • At this point, the boom pull cables should be under tension.
  • Ensure the boom head is elevated approximately 300 mm higher than the boom tail for proper balance.

Notes and Precautions:

  1. Sicherheit geht vor: Constantly monitor the steel wire ropes and hoisting equipment for any irregularities during operation.
  2. Alignment Checks: Ensure that all connecting components, such as pins and bolts, are properly secured after adjustments.
  3. Guidance Cables: Always use guiding cables for the boom head during tower erection to avoid structural collisions.
  4. Operational Efficiency: Coordinate the operation of the hoist with the movement of components to prevent delays and mishaps.
  5. Inspection: Perform a final inspection of all connections, ropes, and support structures to ensure readiness for crane operations.